ZOOMLIEN BLOG

2022 Posts

 

barry's blog banner

Barry Kalmanson, Esq.

Failure to Timely Serve Notice to Owner Under Florida’s Construction Lien Law

Posted on November 14, 2022

Florida law provides that certain lienors (subcontractors, sub-subcontractors and materialmen to contractors, subcontractors or sub-subcontractors) are required to serve notice to owner, failure […]

READ MORE →

barry's blog banner

Barry Kalmanson, Esq.

Methods of Serving Notice to Owner Under Florida’s Construction Lien Law

Posted on May 31, 2022

Florida law provides that a claimant may serve a notice to owner by: Hand delivery; Common carrier delivery service; or Registered, global express guaranteed or certified mail with postage […]

READ MORE →

barry

Barry Kalmanson, Esq.

The Advantage of Serving a Preliminary Notice Early Under Florida’s Construction Lien Law (Notice is Effective as of Mailing)

Posted on March 10, 2022

Florida law provides if a notice to owner on an improvement without a payment bond or a preliminary notice on an improvement with a payment bond is mailed by registered, global express […]